Today was a filing day. All the paperwork, receipts, reports, videos and pictures are piling up and needed to be sorted or lose all value. Below is a 'Before' and 'During Construction' photos of a protected spring.
The Rotary meeting last night was good in that we made some decisions about releasing money to contractors. Basically the first 18 springs are 80% complete but only 30% paid for. So there was some catching up to do, we released some funds today. We have 2.4 million shillings ($30K CDN) over the next 6 weeks so we need to have a system for moving 400,000 Ksh/ week,which is tricky the way banks work down here.
Enough about money, here is some photos:
|
Emulakah PS#13 80% done Jan 26 |
|
Me and Jackson- back-filling and fence behind this wall to be completed |
|
Alot of digging required to ensure water is filtered and spring not flooded |
|
Emulakah PS#13 Before construction Jan 9 |